17th March 2019
Overlooking the world-famous Central Park, this was an exciting project whereby the client undertook a 15-story, out-of-the-ground residential development. Having worked on a broad range of residential schemes around the world, the Linesight team was appointed on the job.
Linesight successfully provided Project, Cost and Schedule Management services for the construction of this residential development. The project included seven luxury residential duplex units spanning over 40,000sq.ft., and overlooking Central Park at the corner of 63rd St and 5th Avenue.
The site location presented a number of challenges for the team; timelines for approval and permitting from the Landmarks and Department of Buildings needed to be factored into the schedule and actively managed. The site also faced Central Park, which posed restrictions around site access, deliveries and timing of work, and this formed an integral part of the planning process, to minimize disruption during construction and ensure program delivery.
Linesight’s scheduling team highlighted issues with the sequencing of work, which in turn helped the general contractor with their means and methods of construction. Ultimately, this resulted in a six-month saving on schedule and reduced overall development costs in excess of 30% on the original budget.
Data
Size
on overall development costs
Patrick Ryan
Executive Vice President – Americas
Americas
Relevant Projects
Latest Insights
19th December 2024
Influential Leader Series – Featuring Brittany Miller, Senior Vice President of Global Development, NTT Global Data Centers
Brittany spoke to Dawn Cantrell, Vice President Americas at Linesight, where they discussed NTT’s role within the fast-changing data center sector, navigating challenges, and advice on mentorship.
Continue Reading20 November 2024
Construction Market Insights H2 2024 – Europe
20 November 2024
Construction Market Insights H2 2024 – Americas
20 November 2024
Construction Market Insights H2 2024 – APAC & GCC