APAC

Healthcare company’s R&D Center in Mumbai

Linesight was engaged by one of the world's largest healthcare companies to deliver Project Management services for the retrofit and construction of its new R&D and Stability Center and Office space in Mumbai.

Key Contact

Ameya Gumaste

Ameya Gumaste

Executive Director and Country Head, India

India

Contact Representative

15th September 2023

Linesight was engaged by one of the world's largest healthcare companies to deliver Project Management services for the retrofit and construction of its new R&D and
Stability Center and Office space in Mumbai.

Linesight’s confidential client continues to develop innovative products and services that benefit people’s health and well-being. The new facility serves as the R&D for global operations and supports product development for its pharmaceuticals division, thus
significantly contributing to India’s growing healthcare industry.
 

Collaboration and teamwork 

The high-tech facility features labs, offices and rooms with mechanical gas piping, lab equipment, a stability chamber, spot extractors and a clean room partition. From a design perspective, instead of dismantling the old structure and rebuilding an entirely new facility, the unique brownfield design maximised the existing structure by adding two levels and building a connection between the new and old buildings, which resulted in cost and time savings and was more environmentally conscious.

Working closely with the client, Linesight demonstrated collaboration and teamwork, effective stakeholder management, developed a micro project development schedule and oversaw the design development and coordination. The project was successfully delivered on time and on budget with overall cost savings. 

Services

  • Overall project management including stakeholder management
  • Vendor management, procurement, and change control
  • Conducted cost risk analysis (CRA) and managed the executive status reports (ESR) as per the client’s global standards 

Value add 

Health and Safety Management 

The team was able to drive innovative ways to
enhance safety, thus contributing to the following achievements:

  • 600,000 safe man hours
  • Zero loss time injury
  • Zero cases of COVID-19 detected onsite  

On time project delivery and cost savings 

COVID-19 happened mid-way through construction which impacted the overall project cost and schedule. The team demonstrated their ability to quickly adapt to the changing situation, managed sponsors’ expectations, and successfully delivered whilst keeping the project costs under control through value engineering.

Construction Supervision 

The facility was built in a live environment with an existing and operational campus within the same area, and in a densely populated residential area with limited surrounding space. The team had to closely monitor the project’s progress to ensure minimal to no disruption to ongoing operations and the wider community.   

Data

Ameya Gumaste

Ameya Gumaste

Executive Director and Country Head, India

India

Latest Insights

20th November 2024

Construction Market Insights H2 2024 – Americas

While both the US and Canadian economies are expected to grow steadily in 2024, the construction markets in these two countries are following divergent trends.

Continue Reading