11th January 2019
As Ireland’s second oldest university, founded in 1795, Maynooth University (MU) currently has more than 8,800 students enrolled. The university has continually invested in its infrastructure, boasting some of Ireland’s most state-of-the-art academic and research facilities. As part of the recent €100 million building program undertaken, the client sought to provide high quality on-campus student accommodation. With a severe shortage of accommodation, both on-campus and in the wider Maynooth area, the university was under pressure to accommodate the large international student contingent. Linesight has an extensive background in delivering cost-effective student residential facilities, without compromising on space or quality.
The Linesight team provided full Cost Management services throughout the project. Considerable effort went into picking the right design solution for the scheme, with numerous options appraised in order to produce a cost-effective, robust, aesthetic and sustainable outcome. Detailed cost studies were undertaken on alternative design solutions for the building structure and fabric – precast cross wall (plate floor, wide slab and hollowcore options), reinforced concrete, structural steel frame and deck with block infill, and various combinations of these. Then benchmark studies were carried out on cost per bed-space and area efficiency, to ensure that the result was consistent with best practice.
Furthermore, as Maynooth University is a public body, the project was procured using the Public Works contracts. It was decided that an Employer Designed route would be the best-fit solution for the client, as it ensured control over the design integrity of the building, coupled with the financial benefit of optimum design decisions.
Due to the urgent requirement for accommodation, a phasing strategy was agreed with MU and the contract was structured to permit the phased handover of units on a block-by-block basis, spanning several months. The first handover occurred in August 2016 – in time for the new academic year. The second handover occurred in October 2016 and the final phase in January 2017.
Data
size
Cost
Brian McCay
Director
Europe
Relevant Projects
Latest Insights
1st November 2024
Why Taiwan needs to develop the quantity surveying profession to remain competitive
This article discusses why Taiwan must develop the quantity surveying profession in the country in order to remain competitive in the global market
Continue Reading